Rapid Response at Seascale

Lanes Group recently delivered an emergency repair following the collapse of a 600mm outfall at Seascale. Working around the clock, specialist teams carried out urgent cleaning and CCTV investigations before completing a permanent repair using bespoke VJ clamps manufactured at short notice. Through expert engineering and a rapid response, the team safely restored the damaged asset, fully reinstated the site and reopened the area within just five days, minimising disruption and restoring the site's infrastructure ahead of the Christmas weekend.

Read the case study here: Rapid Response at Seascale